Under the personal supervision of Edward Mc Guire, Chartered Building Engineer and State Registered Building Surveyor with over 40 years experience a dedicated professional building surveying and construction supervision service.
Our unparalled experience in many aspects of the domestic and commercial construction industry means we are ideally suited to offer our clients a comprehensive building management service. From Planning, design through all construction stages and right through to final certification of compliance with planning permission requirements and building regulations
Construction Project Management
Project Design
Specification and tender processing
Pre planning meetings
Working drawings
Consultations with clients
Selection process and appointment of suitable building contractor
Commencement Notice
Final inspection and certificate of compliance with planning permission and building
Construction Supervision regulations
Interim Valuations and state Payment certifications
" We needed a surveyor to review damage to our house and produce a report for a court case. He also provided invaluable support before and during the case and appeared as an expert witness. Edward was wonderful and without doubt was crucial to the successful outcome of the case. i couldn't recommend him highly enough. "
Lorraine Curran, D, Dublin 14
FAQs
Note: This guidance provides general advice. It is not a legal interpretation of building control Regulations and should not be considered as such. Further guidance can be sought by contacting your technical advisor or your local Building Control Authority.
1. What are the Building Control Regulations?
The Building Control Regulations apply to new buildings, extensions, material alterations and changes of use of
buildings. They promote observance of the Building Regulations by supplementing powers of inspection and
enforcement given to Building
Control Authorities. The Building Control Regulations regulate:
1. Commencement Notices and 7 Day Notices
2. Fire Safety Certificates, Revised Fire Safety Certificates and Regularisation Certificates
3. Disability Access Certificates and Revised Disability Access Certificates
4. Maintenance of Registers
5. Fees
6. Statutory registration of building control activity
Failure to submit a Commencement Notice is an offence and will have serious consequences which cannot be
regularised at a later date. You may have difficulties in selling your property if you cannot prove that the statutory
requirements relevant to the property have been met.
2. What are the Building Regulations?
Building Regulations are a set of legal requirements for the design and construction of new buildings, extensions and material alterations to and certain changes of use of existing buildings. Building Regulations provide for, inrelation to buildings, the health, safety and welfare of people, conservation of fuel and energy, and access for people with disabilities.
3. What is a Commencement Notice?
A Commencement Notice is a notification to a Building Control Authority that a person intends to carry out either works or a Material Change of Use to which the Building Regulations apply. The notice must be given to theauthority not more than 28 days and not less than 14 days before the commencement of works or the change of use. Once validated by the building control authority, works must commence on site within the 28 day period.
4. Do all developments require a Commencement Notice?
Commencement Notices are required for the following:
1. The erection of a building
2. A material alteration of a building
3. An extension to a building
4. A material change of use of a building
5. Works in connection with the material alteration (excluding minor works) of a shop, office or industrial building where a Fire Safety Certificate is not required
A Commencement Notice is not required for:
1. Works or a change of use which requires neither planning permission, nor a Fire Safety Certificate
5. What happens on March 1st 2014?
On the 1st March 2014, new regulations (S.I. 9 of 2014) relating to the commencement and certification of construction works come into effect. For certain building works, the new regulations require that certificates of compliance and other documents must be submitted with the Commencement Notice. The additional requirements also include:
1. The nomination of a competent 'Assigned Certifier' to inspect and certify the works
2. The assignment of a competent builder to carry out the works
3. The submission of Certificates of Compliance on completion
6. Do the additional requirements apply to all Commencement Notices
No. The additional requirements only apply to the following works:
1. Construction of a dwelling house
2. Extension of a dwelling house by more than 40 square meters
3. Works which require a Fire Safety Certificate
7. What additional documents must I submit with my Commencement Notice?
Any Commencement Notice submitted after the 1st March 2014, which come within the scope of S.I. 9 of 2014 must fill out an online assessment of the proposed approach to compliance with the Building Regulations and be accompanied by the following:
1. Certificate of Compliance (Design)
2. Notice of Assignment of Person to Inspect and Certify Works (Assigned Certifier)
3. Undertaking by Assigned Certifier
4. Notice of Assignment of Builder
5. Undertaking by builder
6. General arrangement drawings for building control purposes – plans, sections and elevations
7. A schedule of design documents currently prepared or to be prepared at a later date
8. The preliminary inspection plan
9. Any other documents deemed appropriate by the Assigned Certifier
8. What happens if I do not start work within the statutory notice period of the Commencement Notice?
If the works do not start within 28 days of the date of lodgment of the Commencement Notice, you must submit a new Commencement Notice prior to the commencement of any works taking place.
9. What happens if I don’t submit my Commencement Notice?
Failure to submit a Commencement Notice when required is an offence. If you commence works or a change of use in the absence of a Commencement Notice, there is no provision to retrospectively submit a Commencement Notice. For works subject to S.I. 9 of 2014, you will be unable to submit a Certificate of Compliance on Completion, and your building will not be recorded on the public register. This may affect your ability to lease or sell the building.
10. If I received planning permission before March 1st 2014, am I exempt from the new Regulations?
No. All Commencement Notices received by the Building Control Authority after the 1st March 2014 must comply with the new Regulations
11. Who can act as an Assigned Certifier?
An Assigned Certifier must be:
1. An Architect named on a register maintained pursuant to Part 3 of the Building Control Act 2007, or
2. A Surveyor named on a register maintained pursuant to Part 5 of the Building Control Act 2007, or
3. An Engineer named on a register maintained pursuant to Section 7 of the Institution of Civil Engineers of
Ireland (Charter Amendment) Act 1969
12. Can I build my own house by direct labour?
Yes. You may appoint yourself as the builder if you believe you are competent to carry out that role and sign the Certificate of compliance (Undertaking by Builder). As the builder, you are responsible for compliance with the Building Regulations. You must sign the Certificate of Compliance on Completion and you must also appoint an Assigned Certifier to inspect the works during construction.
13. As an owner, how can I appoint a competent builder?
A competent person may generally be regarded as a person who possesses sufficient training, experience, and knowledge to enable them to undertake the project tasks they are required to perform having regard to the nature of the project and its scale and complexity. Competence can be verified, for instance, by reference to involvement on previous similar projects. One way of choosing a competent builder is to select a builder included on the Construction Industry Register Ireland (CIRI). Further details may be found on www.ciri.ie
14. Who is responsible for compliance with the Building Control Regulations?
The owner of the building, the designer who designs the works, and the builder who carries out the works are responsible, under law, for compliance with Building Regulations and Building Control Regulations.
15. Can I submit my Commencement Notice Online?
Yes, a new national Building Control Management System (BCMS) is now in place. Plans, specifications, particulars, and the preliminary inspection plan can be uploaded to the BCMS. In addition, the online assessment of the proposed approach to compliance with the Building Regulations is also done through the BCMS. The BCMS will allow building owners nominate an Assigned Certifier, and a Builder for the development works. The BCMS will also allow the Owner, Assigned Certifier, and the Builder to fill out the required Notices and Certificates online. Each party must be registered with the BCMS to fill in or sign their respective parts.
16. Can I still submit my Commencement Notice at my local County Council offices?
Yes, Commencement Notices can still be submitted at the offices of your local Building Control Authority. If required, the online assessment must still be carried out via the Building Control Management System.
17. What is the Fee for a Commencement Notice?
The fee for a Commencement Notice is €30, or where the Commencement Notice relates to multiple buildings,€30 in respect of each building. Additional charges will be imposed by the Building Control Authority for commencement notices which are not submitted online via the Building Control Management System.
18. What is a 7 Day Notice?
A 7 day notice is similar to a Commencement Notice and may be used for works, which require a Fire Safety Certificate, when the works need to start before the Certificate is granted. It must be accompanied by a valid Fire Safety Certificate application and a Statutory Declaration. After the 1st March 2014, the additional requirements which apply to Commencement Notices will also apply to 7 Day Notices. The fee for a 7-Day Notice is €250 or €5.80 per square metre of applicable floor area (whichever is the greater).
19. What is a Certificate of Compliance on Completion?
For work coming within the scope of S.I. 9 of 2014, a Certificate of Compliance on Completion must be lodged with the Building Control Authority and placed on the public register before the building may be opened, occupied or used. The Certificate must be signed by the Assigned Certifier and the Builder. It certifies that the building or works have been carried out in accordance with the Building Regulations.
20. What happens if I change my Builder or Assigned Certifier during the construction works?
The owner of the building must notify the Building Control Authority within 14 days of such changes and must submit new Notices of Assignment and undertakings. Failure to do so is an offence.
21. What happens if ownership of the building, development or works changes during construction?
Under the new Regulations, the new owner of the building must notify the Building Control Authority within 14days, in writing. Failure to do so is an offence.